We build new homes and carry out major renovations in the Eastern Townships. With you and your architect, we prepare the work, coordinate construction and track the budget through to handover.

Frontière, a home built by Nu Drom
Frontière — built by Nu Drom
01 — Plan

Start with your architect.

Already working with an architect? We can work with them from the initial sketch stage. An early conversation helps assess ideas against the budget you have in mind, identify points that need attention and consider choices that can simplify construction.

At this stage, a first consultation at no charge helps guide the project, includes a site visit and gives you a chance to see ongoing builds led by our team. At the permit-drawing stage, we begin developing the budget with you and your architect, as the drawings and decisions take shape.

Aerial view of foundations on a Nu Drom site
Preparing the site and the stages ahead.
02 — Build

Know who you are working with.

Your project manager is your point of contact for the budget, schedule and decisions ahead. On site, a dedicated supervisor leads the crew and oversees the work. These two points of contact work closely with to coordinate the trades and review quality at each stage.

With an established presence in the Eastern Townships, Nu Drom has intentionally chosen to limit its growth to maintain a sustained presence on site and consistent quality.

A schedule tracks every stage. Depending on the agreed scope, coordination can extend to exterior work and furniture delivery.

Work on the envelope of a building on a Nu Drom site
People at work, on site.
03 — Live

Receive the home and its records.

At handover, we help you become familiar with the home’s equipment. A file brings together the available drawings, technical information and maintenance records.

The relationship continues after the keys change hands. As needs emerge over the years, Nu Drom remains a point of contact that knows the house and its construction.

Interior of a home built by Nu Drom
Preparing a site for the life that follows.
Construction reporting

See where the work stands.

Regular reporting, generally every two weeks, connects progress, spending and upcoming decisions. The frequency of discussions is adapted to the project.

01The starting budget
The starting budget remains available in the budget reports as a reference throughout the project.
02Changes
Additions, credits and differences are identified so the budget can be followed over time.
03Photographs
Images help explain progress, including when you are away from the site.
04Next decisions
Upcoming work and the choices needed to prepare it.
Du Sommet — concrete fireplace and steel mantel
Du Sommet · Photography: Ian Balmorel
A decision in a completed project

What needs a decision before the pour.

At Du Sommet, the concrete fireplace, window seats and backsplash were poured before the framing. Their dimensions and junctions with timber and glazing therefore had to be prepared early. That work allows the finished details to meet as intended.

Concrete and steel, resolved together.

At Du Sommet, the raw-steel fireplace mantel and its hooks were integrated directly into the concrete. Their thickness, position and anchoring had to be resolved before the pour. The finished junction is the result of that preparation.

Explore Du Sommet →
From our projects

A closer look at construction.

What does building these homes involve? Four projects show the work behind the finished result.

Du Sommet

Cast in the site's own wood

The formwork boards come from trees felled on the site.

The steel shelf is set before the pour: it is part of the concrete.

Read the sequence
  1. Formwork from the site's trees
  2. Steel shelf and anchors
  3. Concrete pour
  4. Stripping
See the project

Construction sequence

Chalet A

Everything comes down the line

The cabin sits at the foot of a very steep site, more than one hundred and ten steps below the road.

A temporary zip line, anchored to two trees, links a platform at the top of the site to another at the bottom.

Read the sequence
  1. Upper platform
  2. Lower platform
  3. Cable, winch and tensioner
  4. Loaded carrier platform
  5. From one platform to the other
See the project

Construction sequence

Steeplechase

Flush door

Closed, the door reads as wall.

Clearances, hardware and movement set so the boards land joint for joint.

Read the sequence
  1. Closed, the door reads as wall.
  2. The top panel drops back at 45°; the door then follows its track.
  3. Clearances, hardware and movement set so the boards land joint for joint.
See the project

Construction sequence

De la Descente

Where the water goes

On either side of the curtain wall, the gutters are cut into the roof slope.

The downspouts run in the outer cavity of a double wall.

Read the sequence
  1. Insulated wall and roof deck
  2. Second wall: the outer cavity
  3. Gutter cut into the slope
  4. Downspout in the outer cavity
  5. Metal roofing
  6. Cladding: everything disappears
  7. The water reaches the gutter
See the project

Construction sequence

Schematic illustrations of the construction sequence.

Questions that come before construction.

What types of work do you take on?

We build new homes and carry out major transformations and architectural additions. Small repairs and minor renovations are not our usual scope.

How is the budget established?

Budget development begins at the permit-drawing stage, with you and your architect. The forecast develops as drawings and decisions take shape, with allowances for items still to be defined. We generally work on a cost-plus basis, under the terms agreed in the contract.

Do I need to have chosen an architect?

If you already have an architect, we work with them. If you are also looking for a design team, a design-build approach with Matière Première Architecture is possible.

When should we get in touch?

From the initial sketch stage, to discuss feasibility, points that need attention and construction choices. Budget development follows at the permit-drawing stage, with you and your architect.

How can I follow the site from elsewhere?

The project manager remains your point of contact. Reporting, generally every two weeks, brings together the updated budget, changes, photographs and upcoming work. Meetings can take place remotely.

Does everything need to be included in one scope?

The scope is agreed with you. We can coordinate exterior work and furniture delivery; some stages after handover can also be entrusted to other parties.