Loft Écurie Ayers Cliff

Ayers Cliff · 2025

The project began with an old barn whose condition made it impossible simply to retain the structure in place. Several elements were too deteriorated and had to be dismantled. Rather than lose what could still be used, however, we carried out a highly selective demolition: salvageable framing members were removed one by one, cleaned, sorted and set aside to be reincorporated into the building. The drawings identify the project as the conversion of the “Loft écurie Ayer’s Cliff.”

The existing foundation was a challenge in itself. It was not square but trapezoidal, with angles that carried through the entire reconstruction. Before rebuilding, we had to reinforce it and work with its existing geometry rather than try to correct it artificially. Every new partition, junction and structural member therefore had to accommodate angles that consistently departed from 90 degrees.

Once the envelope was secured, we rebuilt much of the building using the old framing as an exposed structure. Members that had supported the barn for decades were put back to work in new construction, with all the fitting that entails: none is perfectly straight, no two have exactly the same dimensions, and each must find its place within a structure that has to meet current requirements.

A steel spiral stair sits at the centre of this assembly of old and new. Installing it within a structure made from reused members required very precise coordination of the floor opening, supports and clearances around the stair.

The work was essentially about building anew with old materials: retaining what still had structural value, accepting the irregularities of the original building and successfully integrating them into a precise, durable reconstruction.